DONE Expressway open, ~40 min to AhmedabadBUILDING Airport ~80%, ops targeted Sept-Oct 2026BUILDING Tata fab civil ~50%, first chip target 2026-27LIVE ~300 MW solar commissionedTARGET Semi-high-speed rail target 2030-31DONE Expressway open, ~40 min to AhmedabadBUILDING Airport ~80%, ops targeted Sept-Oct 2026BUILDING Tata fab civil ~50%, first chip target 2026-27LIVE ~300 MW solar commissionedTARGET Semi-high-speed rail target 2030-31
Home › Trackers
Live status board

Dholera project trackers

The real build status of every Dholera mega-project in one board. Each figure is sourced and labelled reported or target. Progress bars are honest indicators, not official completion percentages, and every card links to the full sourced tracker.

Last verified 22 July 2026 · sourced & independent
OPERATIONAL
109 km, 4 lanes100% reported

109 km greenfield access-controlled expressway, 4 lanes expandable to 8, design speed 120 km/h, agency NHAI.

Latest. Reported inaugurated by PM Modi on 31 March 2026 and operational. Travel time Ahmedabad to Dholera cut to roughly 40 minutes to 1 hour.
REPORTED, Mar 2026

Source note: Reported March 2026; cost stated Rs 3,196 cr (construction) to Rs 4,373 cr (with land), conflicting by scope.

Full tracker and sources ›

BUILDING
~80% complete80% reported

Single runway 3,200 m, Code 4E, phase 1. SPV DIACL (AAI 51%, Gujarat 33%, NICDC 16%), about 20 km from the SIR.

Latest. As of 14 July 2026 the Union Aviation Minister reportedly said the airport is about 80% complete, with operations likely September to October 2026.
REPORTED / TARGET, Jul 2026

Source note: Reported 14 July 2026. Original December 2025 target was missed; no firm opening date is confirmed.

Full tracker and sources ›

BUILDING
~50% civil50% reported

Tata Semiconductor Manufacturing, investment Rs 91,000 cr (about US$11B), up to 50,000 wafers per month, 300mm, mature nodes 28 to 110 nm.

Latest. Civil work reported about 50% complete as of May 2026 after a late-2025 redesign for soil conditions. ASML lithography MoU signed 17 May 2026. First chip is targeted for 2026 to 2027.
REPORTED / TARGET

Source note: Union Cabinet approval 29 Feb 2024; Fiscal Support Agreement 5 Mar 2025 (PIB). First chip is a target, not confirmed produced.

Full tracker and sources ›

BUILDING
~300 MW live30% reported

Ultimate announced target 5,000 MW by about 2030. Phase-I 1,000 MW sanctioned, agency Gujarat Power Corporation Ltd.

Latest. About 300 MW commissioned (Tata Power, 1,320 acres). A further 700 MW is under development, targeted March 2027, delayed by tariff and GERC disputes.
OFFICIAL, Sept 2025

Source note: CEA quarterly report as on Sept 2025. The 5,000 MW figure is a long-range target, not installed capacity.

Full tracker and sources ›

TARGET
Target 2030-318% reported

About 134 km double line, cost about Rs 20,667 cr, roughly 45 minute journey. A cited 220 km/h speed is single-sourced and flagged.

Latest. Reportedly cleared by the CCEA around 13 May 2026. Target completion 2030 to 2031. Construction not yet started.
REPORTED / TARGET, May 2026

Source note: Reported May 2026. Confirm cost and speed against PIB before treating as final.

Full tracker and sources ›

OPERATIONAL
Operational100% reported

Administrative cum Business Centre for Dholera in the TP2 Knowledge and IT Zone, houses the Integrated Command and Control Centre, the smart-city brain, LEED Gold design.

Latest. Reported structurally complete and operational, running water, power, lighting, surveillance, traffic and environment monitoring. Exact inauguration date is unknown.
REPORTED

Source note: DICDL official interview 2024; built-up area figures differ by source (about 14,000 to 36,000 sqm), flagged.

Full tracker and sources ›

How to read this. Percentages are indicative, compiled from the latest reported milestone for each project, not an official metric. Dates move. Always confirm a time-sensitive figure against the official source before acting on it. DholeraPulse is independent and does not sell plots.